Subscribe to our free weekly newsletter
Send news

News tags

mental health  physical activity  earthquake  vacancies  families  public health  children  funding  poverty  health determinants  social  Community development  planning  employment  healthy cities  volunteers  newsletter  youth  volunteering  nutrition  employment opportunity  housing  alcohol and drugs  maori  community engagement  rebuilding  wellbeing  disabilities  Lectures  counselling  Training  earthquake recovery  sustainability  event  community gardens  Community  seminar  Awards  stress  Community Groups  mens health  research  arts  smokefree  culture  men  exercise  migrants  community event  education  environment  resilience  human rights  health  medical  business  sport  conferences  survey  mental wellbeing  Courses  obesity  elderly  support group  environmental health  healthy food  health promotion  violence  pacific health  resources  rebuild  women  race relations  meeting  gardens  workshop  services  leadership  forum  water  disabled  repair  transport  prevention  pacific  dance  fundraising  asian health  sexual health  inequality  cancer  support  disasters  development  mindfulness  dementia  presentation  collaboration  health in all policies  data analysis  recovery  smoking  law  drugs and alcohol  technology  safety  cycling  Sleep  policy  parenting  media  hearing  walking  land  neighbours  social justice  qualification  resilient cities  information  community connection  consultation  oral health  bullying  depression  youth empowerment  young people  activities  non-profit  charity  harm  NURSES  addiction  disease  Communication  alcohol  symposium  submission  anxiety  accessibility  Relationships  eating  economics  Advocacy  eLearning  falls  parking  energy  efficiency  heating  insulation  advice  Eating Disorders  abuse  waste  Matariki  webinar  diabetes  workplace  Film  Climate Change  solutions  urban  management  economy  plan  restoration  Report  Vulnerability  welfare  parks  learning  awareness  emergencies  legislation  injury prevention  reading  Meeting Room  conservation  language  refugees  recreation  built environment  data  venue  urban design  Food  older people  finances  suicide  heritage  gender  recycling  breastfeeding  public  identity  Nursing  submissions  Rainbow  biodiversity  campaign  promotion  Gut Health  diversity  therapy  older adults  sexuality  computing  pollution  School Holidays  Arts Therapy  providers  gambling  Maori health  Cervical cancer  screening  trauma  autism  Governance  treaty of waitangi  care  mentoring  pets  relaxation  Professional Development  pornography  exhibition  history  discrimination  vaping  equity  lockdown  grief  rural  hygiene  participation  tourism  summer  intervention  warning  podcast  science  petition  swimming  roadworks  traffic  wildlife  beaches  pools  immunisation  vaccination  brain  preparation  open day  market  evaluation  noise  music  property  testing  crafts  CALD  cultural diversity  camping  creativity  child health  tamariki  climate action  Pasifika  refugee  migrant  community events  road safety  library  Hornby  skills  placemaking  regenerative communities  journey  reflection  regional council  councillors  water management  emergency management  retirement  stress management  Christmas  family  festival  alcohol harm  waterways  planting  health protection  legionnaire's disease  hepatitis  heatwaves  river beds  water safety  natural resources  fishing  gardening  workshops  stormwater  biosecurity  volunteer  plant and animal pest management  politics  faith  crime  drugs  pregnancy  native birds  Waimakariri  water quality  schools  early childhood  health professionals  heart disease  kura  school  ethical issues  rangatahi  Linwood  running  donations  whanau  financial pressures  online  health professional  flooding  conflict  peace  winter  agriculture  stroke 

Settlement secures future for treatment plant

Wednesday, October 9, 2024   Posted in: Signatory Notice Board By: Administrator With tags: waste, water, pollution, services, recovery, repair

Christchurch City Council Newsline: 9th October 2024

An activated sludge reactor will replace the fire-damaged trickling filters at the Christchurch Wastewater Treatment Plant to fix long-standing odour issues impacting local residents.

Christchurch City Council and its insurer have settled an $85 million insurance claim following the fire in 2021, which destroyed two trickling filters at the plant in Bromley.

The filters were a critical part of the sewage treatment process, and the damage impacted the treatment process causing major odour issues that have affected the local community.

The settlement was approved by Councillors unanimously and follows complex negotiations. Confidentiality was required for these negotiations so we could get the best outcome for residents and the environment.

Mayor Phil Mauger said this significant milestone allows the Council to move forward with building both a more resilient and environmentally friendly wastewater treatment plant for the city.

“From the day the fire started, the community has been impacted by the loss of these trickling filters, the stench caused by the interim solution was unbearable.”

“It has been an incredibly distressing time for locals, and we acknowledge this has been a lengthy process. While confidentiality was necessary throughout the negotiations, it resulted in uncertainty for the community over a permanent solution to the fire damage,” Mayor Mauger said.  

“So, I want those directly impacted and all Christchurch residents to know that behind the scenes we have been moving heaven and earth to get to this position today.”

“I want to acknowledge the local Councillors and Community Board Members who have been working hard to make sure residents are heard and their concerns considered. I also want to acknowledge the insurers - settling at this point has meant the Council was able look to an improved solution.”

“We owe it to the people of Christchurch, particularly the surrounding residents, to remove what’s left of the filters and construct an up-to-date new activated sludge system which I am told is lightyears better for treatment and odour control,” the Mayor said.

Design work is underway and it is expected to take up to three years to get the sludge reactors up and running.

“We’re getting on with this permanent fix as quickly as we can. Once the new system has been constructed and commissioned, it will address the odour issues that have been experienced for the last three years,” he said.

Activated sludge reactors are a common and well-known treatment process worldwide, and in New Zealand. It is the best method to treat wastewater from a resilience, growth, sustainability, and long-term cost perspective. 

“The trickling filters are 50 years old, and in that time technology has moved forward in leaps and bounds. This new activated sludge system will provide us with the opportunity to significantly reduce emissions and has a smaller footprint that can be upsized at a lower cost to accommodate our growing population,” Mayor Mauger said.

The current estimate cost is $140 million, which will likely be refined following detailed design. Funding is included in the Long Term Plan so there will be no impact on rates.

“We’ll be able to build the activated sludge reactor without disrupting our current operations. In the meantime, we’re working hard to keep the damaged plant running with minimal odour and will continue to keep the community updated on progress,” the Mayor said.

“Keeping the plant running in its damaged state is challenging and there will always be an element of unpredictability, but our team is experienced and quick to respond to whatever is thrown at them.”

The Council has number of projects underway to improve operation and will continue weekly monitoring of hydrogen sulphide levels in the area around the plant.

Get more information about the Christchurch Wastewater Treatment Plant.

Timeline for the Wastewater Treatment Plant upgrade

It is anticipated the activated sludge reactor will be up and running in about three years. We will have more certainty on the timeline as work progresses.

  • Design:  one year (underway).
  • Construction: two years.
  • Interim operations will continue during construction.
  • The reactor will be commissioned.
  • Interim operations conclude.