mental health  physical activity  earthquake  vacancies  families  public health  children  funding  poverty  health determinants  social  Community development  planning  employment  healthy cities  volunteers  newsletter  youth  volunteering  nutrition  employment opportunity  housing  alcohol and drugs  maori  community engagement  rebuilding  wellbeing  disabilities  Lectures  counselling  Training  earthquake recovery  sustainability  event  community gardens  Community  seminar  Awards  stress  Community Groups  mens health  research  arts  smokefree  culture  men  exercise  migrants  community event  education  environment  resilience  human rights  health  medical  business  sport  conferences  survey  mental wellbeing  Courses  obesity  elderly  support group  environmental health  healthy food  health promotion  violence  pacific health  resources  rebuild  women  race relations  meeting  gardens  workshop  services  leadership  forum  water  disabled  repair  transport  prevention  pacific  dance  fundraising  asian health  sexual health  inequality  cancer  support  disasters  development  mindfulness  dementia  presentation  collaboration  health in all policies  data analysis  recovery  smoking  law  drugs and alcohol  technology  safety  cycling  Sleep  policy  parenting  media  hearing  walking  land  neighbours  social justice  qualification  resilient cities  information  community connection  consultation  oral health  bullying  depression  youth empowerment  young people  activities  non-profit  charity  harm  NURSES  addiction  disease  Communication  alcohol  symposium  submission  anxiety  accessibility  Relationships  eating  economics  Advocacy  eLearning  falls  parking  energy  efficiency  heating  insulation  advice  Eating Disorders  abuse  waste  Matariki  webinar  diabetes  workplace  Film  Climate Change  solutions  urban  management  economy  plan  restoration  Report  Vulnerability  welfare  parks  learning  awareness  emergencies  legislation  injury prevention  reading  Meeting Room  conservation  language  refugees  recreation  built environment  data  venue  urban design  Food  older people  finances  suicide  heritage  gender  recycling  breastfeeding  public  identity  Nursing  submissions  Rainbow  biodiversity  campaign  promotion  Gut Health  diversity  therapy  older adults  sexuality  computing  pollution  School Holidays  Arts Therapy  providers  gambling  Maori health  Cervical cancer  screening  trauma  autism  Governance  treaty of waitangi  care  mentoring  pets  relaxation  Professional Development  pornography  exhibition  history  discrimination  vaping  equity  lockdown  grief  rural  hygiene  participation  tourism  summer  intervention  warning  podcast  science  petition  swimming  roadworks  traffic  wildlife  beaches  pools  immunisation  vaccination  brain  preparation  open day  market  evaluation 

Finish line in sight for Lyttelton Harbour wastewater project

Thursday, October 15, 2020   Posted in: Signatory Notice Board By: Administrator With tags: waste, management, environmental health

Christchurch City Council Newsline: 14th October 2020

A $53 million wastewater project to improve the health of Whakaraupō/Lyttelton Harbour is a step closer to completion.

Four new pump stations have been built around the harbour, to serve as powerhouses to pump all of the Lyttelton Harbour communities’ wastewater over the hill to the main treatment plant in Bromley.

More than five kilometres of submarine pipeline will carry wastewater from Diamond Harbour and Governors Bay to Cashin Quay in Lyttelton, before being piped to the Simeon Quay pump station.

Wastewater will then be pumped through the Lyttelton tunnel and through the newly constructed 4.5 kilometre Heathcote Valley pipeline to Bromley.

Christchurch City Council Head of Three Waters and Waste Helen Beaumont says a lot of work has been done above and below the ground to connect the Lyttelton Harbour's wastewater to the main Christchurch system.

“The Simeon Quay pump station is the biggest one in the Lyttelton Basin, containing three 2.5-tonne pumps, 8-metre-long progressive cavity pumps that have a lot of grunt.

“At its peak, these pumps will be pushing up to 120 litres per second of wastewater uphill through the tunnel at any one time. This will then flow downhill through another 4.5 kilometres of new pipeline to an existing pump station in Woolston," Ms Beaumont says.

The project kicked off in December 2018 and contractors have laid more than 10 kilometres of underground wastewater pipeline, converted three old wastewater treatment plants into pump stations, built one new pump station, and installed countless valves, pipe fittings and chambers to ensure the whole system runs smoothly.

The Lyttelton Harbour wastewater project will end the routine discharge of treated wastewater into the harbour, an important environmental milestone for our city. The new wastewater network will be operational in early 2021, once the entire system has been tested and commissioned.